11/21/2026
10:43 PM
 
Permit No. 25-3605 Permit Type   COMMERCIAL NEW Site Address   400 COSTCO LN
CASTLE ROCK, CO 80109
Applied   09/25/2025 Applicant   Grace Lounsbury
Approved   09/14/2026 Owner   ACM DAWSON TRAILS VIII JV LLC
Issued   09/15/2026 Contractor  
Parent Permit No.   25-3598 Description   COSTCO WHOLESALE FUEL STATION W CANOPY
  Notes  
 
  Date of Inspection Inspection Type Inspector Result Remarks Notes

 10/01/2026B:ELECTRICAL UNDERGRSHAWN VALENZUELAPARTIALeTRAKiT Inspection Request9/29/2026 12:02:09 PM 9/29/2026 12:02 PM CARLTON ELECTRIC INC We are needing a partial underground for the kiosk. Jason Olin is your contact, 303-335-8152. Contact Name: CARLTON ELECTRIC INC Site Address: 400 COSTCO LN Phone: 7208434722 e-Mail: carlylytle@CARLTONELECTRIC.COM 10/1/2026 3:01:24 PM Electrical underground inspection partial approved All ridged metal conduit to be located inside of Kiosk 3/4 1in 2in 3in 1 5/8 ground rod Branch circuit conduits feeding fuel pumps low voltage feeding pumps Branch circuits feeding tanks low voltage feeding tanks Branch circuits feeding canopy Low voltage to tie into existing conduits going to cost co building 2 3in conduits to stub to manual transfer switch All conduit 15 feet underground stub from kiosk to be extended in future (See photo) No conduits installed for electrical service at this time

 10/01/2026PRE CON INSPECTIONBRETT LONGNECKERIN PROGRESSeTRAKiT Inspection Request9/30/2026 8:01:14 AM 9/30/2026 8:01 AM JONES COVEY GROUP, INC. Contact Name: JONES COVEY GROUP, INC. Site Address: 400 COSTCO LN Phone: 6617172412 e-Mail: ELLEN.COLLINS@JFPETROGROUP.COM 10/1/2026 3:58:56 PM Scheduled for 10:00 am Tuesday, October 5th.

 10/09/2026B:UFERSHAWN VALENZUELAAPPROVEDCheck Ufer at the kiosk10/8/2026 11:16:41 AM 10/8/2026 11:16 AM JONES COVEY GROUP, INC. Jose Gurrola 661-717-2412 Contact Name: JONES COVEY GROUP, INC. Site Address: 400 COSTCO LN Phone: 8889727581 e-Mail: ELLEN.COLLINS@JFPETROGROUP.COM 10/9/2026 10:16:02 AM Ufer inspection approved 1/0 bare copper attached to #4 rebar 20 feet in length. 1/0 bare copper to sub into electrical room.

 10/12/2026B:UNGRD PLUMBMARTIN MAGERSPARTIALWater & Sewer10/8/2026 11:59:09 AM 10/8/2026 11:59 AM JONES COVEY GROUP, INC. Jose Gurrola 661-717-2412 Contact Name: JONES COVEY GROUP, INC. Site Address: 400 COSTCO LN Phone: 8889727581 e-Mail: ELLEN.COLLINS@JFPETROGROUP.COM 10/12/2026 11:29:42 AM DWV approved, water line into the unit was not on test. there is a connection cuopling underground outside the unit. Please put on test.

 10/21/2026B:ROUGH PLUMBINGMARTIN MAGERSAPPROVEDcheck for water connection10/20/2026 12:08:19 PM 10/20/2026 12:08 PM JONES COVEY GROUP, INC. water connection. ready for inspection. Jose Gurrola 661-717-2412 Contact Name: JONES COVEY GROUP, INC. Site Address: 400 COSTCO LN Phone: 6617172412 e-Mail: ELLEN.COLLINS@JFPETROGROUP.COM 10/21/2026 12:53:32 PM Corrections made. Water line on test.

 10/27/2026B:ROUGH PLUMBINGMARTIN MAGERSPARTIALJose Gurrola 661-717-241210/26/2026 10:58:17 AM 10/26/2026 10:58 AM JONES COVEY GROUP, INC. water and the venting in the wall Contact Name: JONES COVEY GROUP, INC. Site Address: 400 COSTCO LN Phone: 6617172412 e-Mail: ELLEN.COLLINS@JFPETROGROUP.COM 10/27/2026 10:27:44 AM DWV and Wter lines approved. Still need insulation and heat line.

 10/29/2026B:RE ROUGH PLUMBINGBRETT LONGNECKERAPPROVEDwall insulation and electrical wire.10/28/2026 4:22:43 PM 10/28/2026 4:22 PM JONES COVEY GROUP, INC. wall insulation and electrical wire. wire warmer Contact Name: JONES COVEY GROUP, INC. Site Address: 400 COSTCO LN Phone: 6617172412 e-Mail: ELLEN.COLLINS@JFPETROGROUP.COM 10/29/2026 10:36:00 AM All rough plumbing and underground complete.

 11/10/2026B:ELECTRICAL UNDERGRSHAWN VALENZUELAPARTIALcheck part of the underground electrical11/9/2026 5:15:53 PM 11/9/2026 5:15 PM JONES COVEY GROUP, INC. underground electrical. Check under the canopy to tank hole area. 661-717-2412 Contact Name: JONES COVEY GROUP, INC. Site Address: 400 COSTCO LN Phone: 6617172412 e-Mail: ELLEN.COLLINS@JFPETROGROUP.COM 11/10/2026 2:37:10 PM Electrical underground inspection partial approved Notes 1in conduit x3 at each pump power data veeder root coming from kiosk Camera grey box located outside of kiosk each kiosk column gets conduits and spares and data Warming hut conduits going to kiosk x4 All conduits are 1in Ok to back fill canopy area up to transition sumps. As long as all other mbp are approved Conduits past transition sumps to fuel tanks have not been inspected at this time

 11/13/2026B:ELECTRICAL UNDERGRSHAWN VALENZUELAPARTIALunder ground electrical at the tank hole11/12/2026 3:15:04 PM 11/12/2026 3:15 PM JONES COVEY GROUP, INC. check the underground electrical at tank hole and kiosk service line. Contact Name: JONES COVEY GROUP, INC. Site Address: 400 COSTCO LN Phone: 6617172412 e-Mail: ELLEN.COLLINS@JFPETROGROUP.COM 11/13/2026 10:17:30 AM Electrical underground inspection partial approved Notes 2 3in conduits coming from core transformer to ct cabinet. Recall inspection when conduits are stub to exact transformer location 2 3inch conduit coming from disconnect to manual transfer switch 2 3 inch conduits going for manual transfer switched to inside of building previously inspected Verify bonding #4 fill sumps ground native soil fill sumps #4 cad-welded to ground rod All conduits 1in pvc/ ridged Approved from transition sumps to fill sumps